A free purchase order generator for Australian businesses, what a PO should include, and how to match it to the supplier's invoice.

the short answer

  • A purchase order is the document you send a supplier to order goods or services at an agreed price.
  • Put a PO number, your business and ABN, the supplier, the items and prices, the delivery address and date, and who authorised it.
  • Ask the supplier to quote the PO number on their invoice, then match the two before you pay.
  • The generator below fills it in, adds it up, and prints it or downloads it.

A purchase order, or PO, is the document you send a supplier to order goods or services at a price you've agreed. We found no government rule on what one must include, so the fields below are common practice. It's a record you and the supplier both work from, so the delivery and the invoice can be checked against what you asked for.

Fill in the generator below and it builds the order as you type. Then print it, save it as a PDF, or download the lines for a spreadsheet.

Free purchase order generator

What a purchase order should include

These are the fields in the generator, and why each one is there:

FieldWhy
PO numberThe reference the supplier puts on their invoice, so you can match the two
Your business and ABNWho's ordering, and who the invoice goes to
SupplierWho you're ordering from, and how to reach them
Order date and needed-by dateWhen you ordered, and when it has to arrive
Deliver toThe site or address, which isn't always your office
Items, quantities and pricesExactly what you're buying, at the price you agreed
TotalWith GST shown separately if the supplier charges it
Delivery instructions and payment termsSite access, who to call, and when you'll pay
Authorised byWho approved the spend

The PO number does the most work. Business Queensland lists "Purchase order reference" among the details on an invoice. When the supplier quotes it, every bill points back to the order it came from. Number them in order, the same way you number your jobs.

Purchase order, quote or invoice?

Three documents, sent at three different times:

Supplier's quotePurchase orderSupplier's invoice
Who sends itThe supplierYouThe supplier
WhenBefore you orderWhen you orderAfter delivery
What it saysWhat they'll chargeWhat you're buying, and at what priceWhat you owe, quoting your PO number

Selling rather than buying? You send your customer a quote, and they may send you a purchase order when they accept it.

When a purchase order is worth it

Not every purchase needs one. Business Queensland lists purchase orders among the buying processes worth setting in your financial policies, and names "agreeing on a standard ordering process" as one way to build good supplier relationships. Our suggestion is to use one when:

  • the order is big enough that a mistake would hurt
  • it's being delivered to a site, not picked up
  • someone other than you is placing it
  • it's for a particular job, so the cost can be tracked against it.

Match the invoice before you pay

Before you pay a supplier, check three documents against each other:

  1. The purchase order

    What you ordered, how many, and at what price.

  2. The delivery

    What actually arrived. Check it against the order before you sign for it.

  3. The invoice

    What the supplier is charging, with your PO number on it. Pay it once all three agree.

Keep them, and pay on time

Business Queensland says that "In general you are required to keep records for 5 years", and its record keeping list includes documents relating to purchases. Keep each purchase order with the invoice it matched.

On paying suppliers, Business Queensland suggests periods such as every 14, 21 or 28 days, and setting your customers' terms shorter than your suppliers', so you're not out of pocket. Our guide to payment terms covers the customer side.

From paper to the job

A printed purchase order works until orders are placed from three sites by three people. Then the copies scatter, invoices arrive with no PO number, and nobody knows what a job really cost in materials.

Rather keep job paperwork than retype it? See the apps we're building. None is ready yet, and early access is open. More free generators, from timesheets to quotes, are on our free tools page.

Updated 26 November 2026

questions

Other questions people ask

Something else? Ask us, and we'll answer it.

What is a PO number?
The reference number on a purchase order. The supplier puts it on their invoice. Business Queensland lists a purchase order reference among the details an invoice can carry, so you can match each bill to what you ordered. Number them in order, like PO-0143, PO-0144.
Do I need a purchase order for every purchase?
We found no rule that says so. They're worth it for large orders, orders delivered to a site, and anything someone other than you is ordering. For a small card purchase at the counter, the receipt is enough.
Should a purchase order include GST?
Only if the supplier is registered for GST and charges it. business.gov.au says GST is 10% on most goods and services. The generator adds it as a separate line when you tick the box. The GST itself is charged on the supplier's tax invoice, which business.gov.au says GST-registered businesses must use.
How long should I keep purchase orders?
Business Queensland says that in general you're required to keep records for 5 years, and lists documents relating to purchases among them. Keep each purchase order with its invoice.